Work On I-75 In N Oakland Co Begins In Early March 2024

Metro Detroit Traffic NewsVillage Of Clarkston, MI - Bridge and road work along I-75 in northern Oakland County is expected to resume in early March.

The Michigan Department of Transportation is investing approximately $160 million to resurface and repair I-75 from M-15 (Ortonville Road) to the Oakland/Genesee county line. This project includes resurfacing I-75, repairing 11 bridges, drainage improvements, culvert replacements, signs, and guardrail. Various work will be performed in different locations with different schedules throughout the 15 miles over four years.

This year, northbound I-75 will be milled and resurfaced from M-15 to the county line, with two lanes of northbound and southbound traffic sharing the southbound side of the freeway. Bridge repairs will be performed throughout the project limits along northbound I-75. Work is expected to be completed for the year in late fall.  

In 2025, milling and resurfacing will occur on southbound I-75 from the county line to M-15, with traffic sharing the northbound side. Then in 2026, crews will remove the temporary crossovers and perform the remaining miscellaneous activity. 

Funding for this project is made possible by Gov. Gretchen Whitmer's Rebuilding Michigan program to rebuild the state highways and bridges that are critical to the state's economy and carry the most traffic. The investment strategy is aimed at fixes that result in longer useful lives and improve the condition of the state's infrastructure. 

Based on economic modeling, this investment is expected to directly and indirectly support 1,936 jobs.